Project
|
UA Brigade Facilities Temporary Fire Station |
Location
|
Fort Riley, Kansas |
Organization
|
Alutiiq, LLC / US Army |
Facility Type
|
Emergency Response |
Provided turn-key design-build services for this facility. Facility consists of Kelly Klosure buildings on a concrete foundation, offices, bunk rooms, apparatus bay, restrooms/showers, equipment decontamination area, anti-terrorism windows & doors, HVAC, fire sprinkler & alarm systems, electrical. The building shell was erected in 10 working days. Because of the nature of the need, the building is designed to meet the Army’s requirements for a re-locatable facility. No more than 20% of the building cost can be left behind in relocation.